Project Level Activity Plan


Project Start Date: Mon 02/08/04
Project Finish Date: Tue 21/03/06

Task_Table1

ID

Name

Duration

Start_Date

Finish_Date

1

Project Initiation

71 days

Mon 02/08/04

Mon 08/11/04

2

Completion of Project Mandate

3 days

Mon 02/08/04

Wed 04/08/04

3

Appointment of Project Executive and Project manager

2 days

Thu 05/08/04

Fri 06/08/04

4

Appointment of Project Board

35 days

Mon 13/09/04

Fri 29/10/04

5

Presentation of Project Brief and Project Approach

0 days

Mon 08/11/04

Mon 08/11/04

6

Project Board Authorisation to Proceed

0 days

Mon 08/11/04

Mon 08/11/04

7

Presentation of Project Initiation Document and 1st Stage Plan

0 days

Mon 08/11/04

Mon 08/11/04

8

Project Board Authorisation to Proceed

0 days

Mon 08/11/04

Mon 08/11/04

9

Stage 1

128 days

Tue 09/11/04

Fri 20/05/05

10

Identify Network Monitoring Tools

8 days

Tue 09/11/04

Thu 18/11/04

11

Product search

2 days

Tue 09/11/04

Wed 10/11/04

12

Request and receipt of product literature (hard copy or electronic)

5 days

Thu 11/11/04

Wed 17/11/04

13

Creation of summary list

1 day

Thu 18/11/04

Thu 18/11/04

14

Evaluate Network Monitoring Tools

6 days

Fri 19/11/04

Fri 26/11/04

15

Create list of requirements

1 day

Fri 19/11/04

Fri 19/11/04

16

Create list of evaluation criteria

1 day

Fri 19/11/04

Fri 19/11/04

17

Undertake product literature appraisal and review (first level)

4 days

Mon 22/11/04

Thu 25/11/04

18

Arrange and attend product vendor(s) on-site demonstration (second level)

1 day

Fri 26/11/04

Fri 26/11/04

19

Undertake test bed evaluation of shortlisted products (third level)

0 days

Fri 26/11/04

Fri 26/11/04

20

Produce Evaluation Report

0 days

Fri 26/11/04

Fri 26/11/04

21

Produce Recommedations

0 days

Fri 26/11/04

Fri 26/11/04

22

Procure Network Monitoring Tools

0 days

Fri 26/11/04

Fri 26/11/04

23

Receipt of quotation from preferred product supplier/vendor

0 days

Fri 26/11/04

Fri 26/11/04

24

Identify procurement route

0 days

Fri 26/11/04

Fri 26/11/04

25

Process purchase order

0 days

Fri 26/11/04

Fri 26/11/04

26

Delivery receipt

0 days

Fri 26/11/04

Fri 26/11/04

27

Process invoice

0 days

Fri 26/11/04

Fri 26/11/04

28

Implementation of Network Monitoring Tools

0 days

Fri 26/11/04

Fri 26/11/04

29

Installation

0 days

Fri 26/11/04

Fri 26/11/04

30

Testing

0 days

Fri 26/11/04

Fri 26/11/04

31

Commissioning

0 days

Fri 26/11/04

Fri 26/11/04

32

Monitoring of Broadband Network

10 days

Mon 29/11/04

Fri 10/12/04

33

Problem identification and resolution

10 days

Mon 13/12/04

Mon 10/01/05

34

Consolidation of existing developments

72 days

Mon 15/11/04

Wed 09/03/05

35

Consolidation of v. 1 Managed Service Primary Schools

61 days

Mon 29/11/04

Tue 08/03/05

36

Prepare User Briefing Notes

5 days

Mon 29/11/04

Fri 03/12/04

37

Circulate User Briefing Notes

35 days

Mon 06/12/04

Mon 07/02/05

38

Birchgrove Junior

1 day

Mon 06/12/04

Mon 06/12/04

39

Cwmbwrla Primary

1 day

Mon 06/12/04

Mon 06/12/04

40

Cwmrhydyceirw Primary

1 day

Mon 06/12/04

Mon 06/12/04

41

Danygraig Primary

1 day

Mon 07/02/05

Mon 07/02/05

42

Gors Priumary

1 day

Mon 07/02/05

Mon 07/02/05

43

Hafod Primary

1 day

Mon 06/12/04

Mon 06/12/04

44

Manselton Primary

1 day

Mon 07/02/05

Mon 07/02/05

45

Morriston Primary

1 day

Mon 06/12/04

Mon 06/12/04

46

Newton Primary

1 day

Mon 07/02/05

Mon 07/02/05

47

Parkland Primary

1 day

Mon 07/02/05

Mon 07/02/05

48

Pennard Primary

1 day

Mon 07/02/05

Mon 07/02/05

49

Pentrechwyth Primary

1 day

Mon 07/02/05

Mon 07/02/05

50

Penyrheol Primary

1 day

Mon 07/02/05

Mon 07/02/05

51

Pontardulais Primary

1 day

Mon 07/02/05

Mon 07/02/05

52

Terrace Road Primary

1 day

Mon 07/02/05

Mon 07/02/05

53

Relocate users to Global Users group and undertake post-implementation test check

55 days

Tue 07/12/04

Tue 08/03/05

54

Birchgrove Junior

0.5 days

Tue 07/12/04

Tue 07/12/04

55

Cwmbwrla Primary

0.5 days

Tue 07/12/04

Tue 07/12/04

56

Cwmrhydyceirw Primary

0.5 days

Wed 08/12/04

Wed 08/12/04

57

Danygraig Primary

1 day

Mon 21/02/05

Mon 21/02/05

58

Gors Priumary

1 day

Tue 22/02/05

Tue 22/02/05

59

Hafod Primary

0.5 days

Thu 09/12/04

Thu 09/12/04

60

Manselton Primary

1 day

Wed 23/02/05

Wed 23/02/05

61

Morriston Primary

0.5 days

Fri 10/12/04

Fri 10/12/04

62

Newton Primary

1 day

Thu 24/02/05

Thu 24/02/05

63

Parkland Primary

1 day

Fri 25/02/05

Fri 25/02/05

64

Pennard Primary

1 day

Mon 07/03/05

Mon 07/03/05

65

Pentrechwyth Primary

1 day

Tue 08/03/05

Tue 08/03/05

66

Penyrheol Primary

1 day

Wed 02/03/05

Wed 02/03/05

67

Pontardulais Primary

1 day

Thu 03/03/05

Thu 03/03/05

68

Terrace Road Primary

1 day

Fri 04/03/05

Fri 04/03/05

69

Consolidation of v. 2 Managed Service Primary Pilot Schools

4 days

Tue 11/01/05

Fri 14/01/05

70

Consolidation of v. 2 Managed Service Secondary Pilot School

4 days

Tue 11/01/05

Fri 14/01/05

71

Consolidation of Server Farm

54 days

Mon 15/11/04

Fri 11/02/05

72

Review current layout of data cabinet and equipment

30 days

Mon 15/11/04

Mon 10/01/05

73

Evaluate of current layout

24 days

Tue 11/01/05

Fri 11/02/05

74

Identify and record any improvements

24 days

Tue 11/01/05

Fri 11/02/05

75

Implement any improvements

24 days

Tue 11/01/05

Fri 11/02/05

76

Record final accepted data cabinet and equipment layout

24 days

Tue 11/01/05

Fri 11/02/05

77

Complete Asset Installation sheet for each item

15 days

Tue 11/01/05

Mon 31/01/05

78

Complete configuration information documentation

24 days

Tue 11/01/05

Fri 11/02/05

79

Complete Network Patching Record

24 days

Tue 11/01/05

Fri 11/02/05

80

Review of warranty and maintenance arrangements

5 days

Tue 11/01/05

Mon 17/01/05

81

Documenting of warranty and maintenance arrangements

5 days

Tue 18/01/05

Mon 24/01/05

82

Input of warranty and maintenance arrangements to ASSYST CMDB

5 days

Tue 25/01/05

Mon 31/01/05

83

Interim Implementation of New Developments

18 days

Mon 14/02/05

Wed 09/03/05

84

Interim implementation of new developments - Cefn Hengoed Community School

9 days

Mon 14/02/05

Thu 24/02/05

85

Local Implementation

7 days

Mon 14/02/05

Tue 22/02/05

86

Implement NAS Server (Data storage)

1 day

Mon 14/02/05

Mon 14/02/05

87

Record documentation on implementation and configuration of NAS Server (Data storage)

1 day

Mon 14/02/05

Mon 14/02/05

88

Implement Domain Controller (Local)

1 day

Tue 15/02/05

Tue 15/02/05

89

Record documentation on implementation and configuration of Domain Controller (Local)

1 day

Tue 15/02/05

Tue 15/02/05

90

Implement UPS

1 day

Wed 16/02/05

Wed 16/02/05

91

Record documentation on implementation and configuration of UPS

1 day

Wed 16/02/05

Wed 16/02/05

92

Implement Data switch(es)

1 day

Thu 17/02/05

Thu 17/02/05

93

Record documentation on implementation and configuration of Data switch(es)

1 day

Thu 17/02/05

Thu 17/02/05

94

Implement Workstation (migration)

1 day

Fri 18/02/05

Fri 18/02/05

95

Record documentation on implementation and configuration of Workstations (migration)

1 day

Fri 18/02/05

Fri 18/02/05

96

Record documentation on training undertaken

1 day

Mon 21/02/05

Mon 21/02/05

97

Undertake ad hoc training for ICT Co-ordinator / Technician on system administration and use

1 day

Tue 22/02/05

Tue 22/02/05

98

Central Implementation

2 days

Wed 23/02/05

Thu 24/02/05

99

Implementation of MS Exchange

1 day

Wed 23/02/05

Wed 23/02/05

100

Record documentation on implementation and configuration of MS Exchange

1 day

Wed 23/02/05

Wed 23/02/05

101

Implementation of Data back-up

1 day

Thu 24/02/05

Thu 24/02/05

102